| No. | Uraian | SAT. | Koef. | Harga Satuan (Rp) |
Jumlah (Rp.) |
Referensi Harga |
|---|---|---|---|---|---|---|
| A | TENAGA KERJA | |||||
| Pekerja Listrik | OH | 0,0310 | 150.000 | 4.650 | Link | |
| Tukang Listrik | OH | 0,0310 | 250.000 | 7.750 | Link | |
| Kepala Tukang | OH | 0,0060 | 275.000 | 1.650 | Link | |
| Mandor | OH | 0,0020 | 300.000 | 600 | Link | |
| b. Jumlah Harga Pekerja | 14.650 | |||||
| B | BAHAN | |||||
| Kabel NYM 3 x 1.5 mm2 | Meter | 1,2000 | 22.500 | 27.000 | Link | |
| a. Jumlah Harga Bahan | 27.000 | |||||
| C | ALAT KERJA | |||||
| Peralatan | Lot | 1,0000 | 10.000 | 10.000 | Link | |
| c. Jumlah Harga Alat | 10.000 | |||||
| d. Total (a+b+c) | 51.650 | |||||
| e. Keuntungan 10% | 5.165 | |||||
| Harga Satuan Pekerjaan (d+e) | 56.815 | |||||
| Pembulatan Harga Harsat | 56.800 | |||||