| No. | Uraian | SAT. | Koef. | Harga Satuan (Rp) |
Jumlah (Rp.) |
Referensi Harga |
|---|---|---|---|---|---|---|
| A | TENAGA KERJA | |||||
| Pekerja | OH | 0,7500 | 150.000 | 112.500 | Link | |
| Mandor | OH | 0,0250 | 300.000 | 7.500 | Link | |
| b. Jumlah Harga Pekerja | 120.000 | |||||
| B | BAHAN | |||||
| Galian Tanah | m3 | 1,0000 | 0 | 0 | Link | |
| a. Jumlah Harga Bahan | 0 | |||||
| C | ALAT KERJA | |||||
| Peralatan | Lot | 1,0000 | 10.000 | 10.000 | Link | |
| c. Jumlah Harga Alat | 10.000 | |||||
| d. Total (a+b+c) | 130.000 | |||||
| e. Keuntungan 10% | 13.000 | |||||
| Harga Satuan Pekerjaan (d+e) | 143.000 | |||||
| Pembulatan Harga Harsat | 143.000 | |||||